CET Energy Completes Construction of ss 220/20 kv for Solar Power Plant Hodovo

Successfully completed construction of a 220/20 kV substation for solar power plant Hodovo, for the Investor ECO-WAT d.o.o. Kiseljak, Bosnia and Herzegovina.

Scope of this project was design, procurement, and construction of the SS 220/20 kV. CET Energy scope includes:

  • Equipment procurement and delivery of protection and control system and SCADA system
  • Engineering and documentation design
  • Testing and commissioning of HV and MV switchgears, protection and control system and SCADA system

Project Significance

This project represents a significant contribution to Bosnia and Herzegovina's renewable energy goals.

Project Completion: TS 110/10 kV IGM TREJD

CET Energy, as Consortium leader, successfully completed the SS 110/10 kV IGM Trejd project.

The subject of the Contract was project documentation design, equipment delivery (protection and control system, SCADA system), works and services (engineering, installation, testing and commissioning, customer training).

 

110/10 kV TS IGM Trejd -SINVIR PROEKT (youtube.com)

Contract for construction of SS 110/10 kV IGM Trejd

The project "Construction SS 110/10 kV IGM Trejd with Investor IGM TREJD d.o.o. Kavadarci, R.N. Macedonia" was successfully completed.

Scope of the Contract was equipment delivery that includes protection&control system and other complete secondary equipment.

Scope of contracted works was engineering and electric installation works on complete station.

CET Energy Signs Contract for Reconstruction of SS 110/x Novi Travnik

Signed Contract for the reconstruction of the 110/x kV substation Novi Travnik, Bosnia and Herzegovina, for the Investor Elektroprenos BiH a.d. Banja Luka.

The subject of the Contract is project documentation design, equipment delivery (protection and control system, SCADA system, auxiliary power supply equipment), works and services (engineering, installation, testing and commissioning, control room renovation, customer training).

Signed Contract for reconstruction of SS 110/x kV Novi Travnik

CET Energy has signed Contract for reconstruction SS 110/x kV Novi Travnik with Investor Elektroprenos BiH a.d. Banja Luka , Bosnia and Herzegovina.

Scope of work is procurement and delivery of equipment and execution of works that includes protection&control system and other complete secondary equipment

Scope of contracted works are engineering and electric installation works on complete station which include:
- project management,
- project documentation design,
- delivery and installation of equipment (protection and control system, SCADA system and auxiliary power supply equipment)
- parameterization of protection-control devices,
- parameterization of RTU/Gateway and HMI (SCADA),
- testing and commissioning,
- training for the Client's staff.

Signed Contract for construction of SS 220/20 kV of the solar power plant Hodovo

CET Energy as member of the consortium has signed Contract for construction SS 220/10 kV of the solar power plant Hodovo with Investor ECO-WAT d.o.o. Kiseljak, Bosnia and Herzegovina.

Scope of work is procurement and delivery of equipment and execution of works that includes protection&control system and other complete secondary equipment.

Scope of contracted works are engineering and electric installation works on complete station which include:
- delivery and installation of protection and control system equipment and SCADA system,
- Project documentation design,
- parameterization of protection-control devices,
- parameterization of RTU/Gateway and HMI (SCADA),
- testing and commissioning (HV and MV equipment, protection and control equipment, RTU/Gateway and HMI - SCADA equipment).

Signed Contract for ss 220/20 kv for Solar Power Plant hodovo

CET Energy signed a subcontract for the construction of a 220/20 kV substation for solar power plant Hodovo, for the Investor ECO-WAT d.o.o. Kiseljak, Bosnia and Herzegovina.

Scope of this project is design, procurement, and construction of the SS 220/20 kV. CET Energy scope includes:

  • Equipment procurement and delivery of protection and control system and SCADA system
  • Engineering and documentation design
  • Testing and commissioning of HV and MV switchgears, protection and control system and SCADA system

Project Significance

This project represents a significant contribution to Bosnia and Herzegovina's renewable energy goals.

CET Energy remains committed to supporting the development of renewable energy infrastructure in Bosnia and Herzegovina. We look forward to sharing updates on the progress of the Hodovo solar power plant substation project.

CONTRACT SIGNED FOR CONSTRUCTION OF TS 110/10 KV IGM TREJD

CET Energy, as Consortium leader, has signed a Contract for the construction of SS 110/10 kV IGM Trejd with the Investor IGM TREJD d.o.o., Kavadarci, North Macedonia.

The subject of the Contract is project documentation design, equipment delivery (protection and control system, SCADA system), works and services (engineering, installation, testing and commissioning, customer training).

PARTICIPATION AT 15th CONFERENCE BH K/O CIGRE

From 17.10.2021. to 20.10.2021. EGO - smart electric vehicle (EV) charging stations system which includes charging equipment with reservation functions and smart billing system was presented at 15th BH K/O CIGRE.

EGO is developed withing the project: „Poticaj razvoju novih tehnologija električne mobilnosti u BiH“ in cooperation with international partner IMPLERA d.o.o. Slovenska Bistrica and with financial support from „Fond za zaštitu okoliša Federacije BiH“.

More information about EGO charging system is available by clicking „EGO-CHARGING“ at the top of the page and also via contact form at CET Energy d.o.o. web site.

„Fond za zaštitu okoliša Federacije BiH“ web site: www.fzofbih.org.ba

This content is responsibility of CET Energy d.o.o. Sarajevo and it does not necessarily represent the stand of „Fond za zaštitu okoliša Federacije BiH“.